Project Summary


In conjunction with bi-directional modification efforts to their Rockies Express (REX) pipeline, Tallgrass Energy Partners is enhancing their overall system to allow for an additional 800 MMscfd from the east end of REX to market opportunities in the west. The REX Zone 3 Capacity Enhancement Project increased the system’s delivery capacity from 1.8 Bcfd to 2.6 Bcfd by adding three (3) new compressor stations and modifying two (2) existing compressor stations.

HBK's oil and gas team acted as the general contractor and performed the project management, engineering, procurement, and construction (EPC). Construction was completed on schedule.

Below are the major equipment requirements for the compressor stations:


Chandlersville CS – Existing Station

  • Three (3) Solar Mars 100/C45 Turbine-Driven Compressor Packages (total HP 38,400)
  • Three (3) inlet filter coalescers and three (3) discharge filter coalescers
  • Eleven (11) gas after coolers equipped with low noise mag fans
  • One (1) emergency generator
Tallgrass REX Zone 3

Columbus CS – New Station

  • Four (4) Solar Mars 100/C45 Turbine-Driven Compressor Packages (total HP 51,344)
  • Three (3) inlet filter coalescers
  • Ten (10) gas after coolers equipped with low noise mag fans
  • One (1) emergency generator

Washington Court House CS – New Station

  • Two (2) Solar Mars 90/C45 and One (1) Mars 100/C45 Turbine-Driven Compressor Packages (total HP 32,155)
  • Three (3) inlet filter coalescers
  • Seven (7) gas after coolers equipped with low noise mag fans
  • One (1) emergency generator

Hamilton – Existing Station

  • Eight (8) gas after coolers equipped with low noise mag fans
  • St. Paul CS – New Station
  • Three (3) Solar Mars 100/C45 Turbine-Driven Compressor Packages (total HP 38,469)
  • Three (3) inlet filter coalescers
  • Six (6) gas after coolers equipped with low noise mag fans
  • One (1) emergency generator